Built by our own crews.

We build the underground pathways that protect and organise utility infrastructure across Alberta, from precast vaults and manholes to multi-way concrete-encased conduit banks. Precise forming, rebar and concrete work is what separates a ductbank that passes acceptance from one that gets rebuilt.

Concrete-encased work is unforgiving. Once the pour is complete, an error in spacing, grade or alignment is no longer a correction. It is a demolition. Spacer racking, rebar and formwork are verified against the drawing before a yard of concrete is placed.

Every duct is mandrel-proofed and rope-installed before handover, and the as-built records the actual invert, alignment and duct assignment. The next contractor to pull cable through your corridor gets a system that works on the first attempt.

AT A GLANCE
Typical clients
Carriers, utilities and prime contractors
Sectors
Downtown cores, utility corridors, industrial sites and campuses
Crew
Forming and concrete crews with picker support
Equipment
Excavators, pickers and cranes, laser levels, total stations, vibrators and compactors
Deliverables
Mandrel and proof test records, concrete tickets and as-builts
02 / CAPABILITIES

Scope we self-perform.

Single and multi-way duct banks
Concrete encasement to specification
Rebar fabrication and tying
Precast manhole and vault setting
Handhole and pull-box installation
Conduit terminations and bell ends
Sealed entries and pulling irons
Cable tray and rack systems
03 / HSE

Safety is the schedule.

DAILY HAZARD ASSESSMENTS

Every shift opens with a documented field-level hazard assessment, signed by every worker on site.

ALBERTA OHS COMPLIANCE

Programs, training records and equipment certifications maintained current to Alberta OHS and audited by third parties.

CLIENT SITE-SPECIFIC ORIENTATION

Our crews complete your site orientation and prime-contractor requirements before the first day of work.

05 / FAQ

Frequently asked questions.

Yes, we employ our own forming and concrete crews supported by in-house equipment. Spacer racking, rebar and formwork are strictly verified against the drawing before any concrete is placed.